Iran Putting Damaged Oil Capacity Back on Track, Minister Says
Part of the oil-industry capacity lost in the third imposed war should be available by the end of the Iranian year in March 2027, after the cold season, and the rest in the first half of the following year, Oil Minister Mohsen Paknejad said.
RoydadNaft – Part of the oil-industry capacity lost in the third imposed war should be available by the end of the Iranian year in March 2027, after the cold season, and the rest in the first half of the following year, Oil Minister Mohsen Paknejad said.
Reconstruction of four gas refineries and of liquid-fuel storage and loading facilities in Tehran that were hit is going well, he told Roydad Naft. Execution arrangements are finalized. A large workforce is on the rebuild, and progress can be tracked week by week, he said.